Tubod, Lanao del Norte - Power
supply in Mindanao is more than enough to supply electricity almost doubled the
Mindanao capacity need.
The
Lanao del Norte Electric Cooperative (LANECO) has a pending Energy Regulatory
Commission (ERC) case No. 2016-108 RC, for a joint application for approval of
the Power Supply Contract (PSC) entered into by and between the LANECO, Inc.
and San Miguel Consolidated Power Corporation (SMCPC), with prayer for
confidential treatment of information.
According
to source, LANECO has a total power capacity at 12 megawatt (MW) to supply
power to consumers but only an average of 8 MW is consumed in a month. The KP
members in Lanao del Norte observed that in their power billing they paid was
approximately increased to PhP15.00 per kWh started in December 2016 from
PhP9.00 per kWh without prior notice.
Currently,
the LANECO has a new power supply contract (PSC) with San Miguel Consolidated
Power Corporation (SMCPC) and jointly applied to ERC for its approval
The members of the kilusang Pagbabago (KP) Lanao del Norte (LDN) chapter who are also power
consumers questioned the contract application with prayer for confidentiality which
already contradict to the transparent and accountable governance. The KP LDN
also questioning the rationality of the power supply application because
allegedly in 2016 the load capacity received from suppliers of LANECO is 12 MW
but the load distributed to member-consumers is only 8 MW, therefore, there is
an excess power of 4 MW. There is also an existing problem in LANECO of an
excessive unpaid electricity in huge amounts uncollected that allegedly charge
it to the system loss.
Engineer
Norberto J. Oller, the Past President and Technical Analyst of the Lanao Power
Consumers Federation (LAPOCOF) and the current Consultant of the Iligan City
Government, said that the system loss can be measure the losses of energy
connecting from the supplier substation to transmission then distribution to
the consumers. He said in the RA 9136 or the Energy Power Industry Reform Act
(EPIRA), the maximum allowed charges on system loss is only a maximum of 9
percent based on the actual usage of electricity.
The
Mindanao Power Monitoring Committee (MPMC) held a meeting of Principals on 15
November 2016 at Diamond Hotel, Manila was hosted by the Department of Energy -
Electric Power Industry Management Bureau (DOEEPIMB).
The
summary of Mindanao power projects as of October 31, 2016 have two components,
the COMMITTED power capacity and the INDICATIVE power capacity. The committed
power capacity is the power usages actually consumed while the Indicative power
capacity comprises the power actually consumed and the excess power also known
as reserve power.
The
Committed power has a total capacity to 1,687.9 megawatt (mw), with 17
proponents, comprising the coal-fired power source with 5 proponents or power
plants have total capacity of 1,501 mw equivalent to 89.5 percent share
contribution to the overall power capacity; oil-based have 4 proponents with
total power capacity of 29.5 mw equivalent to 1.7 percent share; natural gas is
zero percent share; renewable energy have 8 proponents with power capacity of
148.4 mw equivalent to 8.8 percent share; Under the Renewable energy,
geothermal with zero percent share, hydro with 8 percent share composed of 5
proponents with a total capacity of 134.2 mw, Biomass have 3 proponents with
total capacity of 14.2 mw with 0.8 percent share, solar and wind energy have
zero percent share.
The
Indicative power has a total capacity of 2,765.8 mw with 37 proponents,
comprising the coal-fired power source with 6 proponents or power plants has a
total capacity of 1,733 mw equivalent to 62.7 percent share contribution to the
overall power capacity; oil-based has 3 proponents with total capacity of 30.9
mw equivalent to 1.1 percent share; natural gas has zero percent share;
renewable energy has 28 proponents with total capacity of 1,001.9 mw equivalent
to 36.2 percent share. Under the renewable energy, geothermal has 1 proponent
with power capacity of 40 mw equivalent to 1.4 percent share, hydro has 17
proponents with total power capacity of 662.7 mw equivalent to 24 percent
share, Biomass with 5 proponents has a total capacity of 61.2 mw equivalent to
2.2 percent share, solar power has 5 proponents with indicative power capacity
of 238 mw equivalent to 8.6 percent share and wind energy have zero percent
share.
The
Challenges in Mindanao power sector generation identified the excess
generation, Policy on embedded Generation, Transition to a Competitive
Environment, Marketing of the Excess Capacity to Investors. The Challenges on
the TRANSMISSION operations is the Security of Transmission Facilities, Timely
Completion of Transmission Projects, DISTRIBUTION collection efficiency, Supply
contracting Issues.
In
a mindset, the excess power generation is the difference of the Indicative
power capacity of 2,765.8 MW and Committed power capacity of 1,687.9 MW.
Therefore the excess power in Mindanao for 2016 is estimated to 1,077.9 MW.
A projection from the power sector for 2017 has total projected installed capacity of 3,577.67 MW while total projected demand is 1,704 MW only. For 2018 projection, the installed capacity is 4,282.67 MW with projected demand is only 1,832 MW. For 2019 projection, an installed capacity at 4,282.67 MW with total power demand at 1,950 MW. For 2020 projection, the total installed capacity is 4,282.67 MW and the total projected demand is 2,097 MW only. Therefore, on 2021 the projected power surplus is 2,165.67 MW.
The National Grid Corporation of the Philippines (NGCP) keep mum on this matter as they were invited during the Media Summit for Northwestern Mindanao held in Iligan City on November 28-29, 2016, to shed light on the power issues and concerns but to no avail reasons they cannot be reached from a very short distance within the vicinity of Iligan City.
A projection from the power sector for 2017 has total projected installed capacity of 3,577.67 MW while total projected demand is 1,704 MW only. For 2018 projection, the installed capacity is 4,282.67 MW with projected demand is only 1,832 MW. For 2019 projection, an installed capacity at 4,282.67 MW with total power demand at 1,950 MW. For 2020 projection, the total installed capacity is 4,282.67 MW and the total projected demand is 2,097 MW only. Therefore, on 2021 the projected power surplus is 2,165.67 MW.
The National Grid Corporation of the Philippines (NGCP) keep mum on this matter as they were invited during the Media Summit for Northwestern Mindanao held in Iligan City on November 28-29, 2016, to shed light on the power issues and concerns but to no avail reasons they cannot be reached from a very short distance within the vicinity of Iligan City.
In
the Power Supply Contract (PSC), the LANECO will serve as the Buyer and the
SMCPC will be the Seller. The joint application was submitted to the Energy
regulatory Commission on March 14, 2016 for approval. It was stated in its
application that there was two separate biddings conducted by the LANECO bids
and awards committee with two separate biddings and have had two bidders failed
and only none bidder was qualified, the SMCPC.
In
its application historical background, on March 1, 2016, LANECO Bids and Awards
committee (BAC) issued a resolution no. 10 to have a direct negotiation with
SMCPC for the procurement of 5 MW electric energy for the period of 2016 to
2026 equivalent for 10 years. On March 3, 2016, LANECO Acting General Manager,
invited the SMCPC for a negotiation of its power supply.
On
March 4, 2016 the LANECO technical working group issued a resolution No. 01 endorsing
to LANECO Board of Directors through its management headed by Mr. Mañada
to enter into a Power supply contract (PSC) to SMCPC.
On
March 7, 2016, the LANECO Board of Directors issued a Resolution No. 26,
authorizing its President, Mr. Emmanuel A. Mejorada, to sign the PSC with SMCPC
for the supply of 5 MW electric energy to LANECO for the period of 2016 to 2026
equivalent to 10 years. On march 14, 2016 the LANECO and SMCPC executed the PSC
subject to the joint application.
In
the contract the buyer shall maintain a minimum hourly nomination at least 40
percent of the contract capacity for a duration of the PSC, as its share in the
minimum stable load of the power plant. The generation source of the electric
power supply of SMCPC is coming from its ongoing construction of a 2 x 150 MW
circulating fluidized bed coal-fired power thermal power plant, located in
Culaman, Malita, Davao del Sur, which was expected to be commercially
operational in the first quarter of 2016.
The
effectivity of the PSC shall take effect between the parties on the date of
signing and shall remain effective for a period of ten (10) years from
commercial operation date (COD). The supply of the electric power by the seller
shall commence upon COD, and shall continue until the end of the contract term.
The
KP in Lanao del Norte doubted the LANECO and SMCPC PSC is an anomalous contract
cited the existing power capacity of LANECO is more than enough to supply the
electric power requirement in the province of Lanao del Norte. The supply of 5
MW will be considered as an excess power. LANECO has an existing contract with
electric power suppliers plus an additional contract of SMCPC in layman’s
understanding and simple arithmetic is addition which already exceeded the
power supply in the province of Lanao del Norte.
The
LANECO management through its Acting General Manager, Sherwin Mañada, invited
the Kilusang Pagbabago (KP), Lanao del Norte (LDN) chapter through John Gandi
Y. Amores, Coordinator, to attend for the Jurisdictional requirements,
Expository presentation, Pre-trial conference and presentation of evidence on
March 16, 2017 at 9:00 O’clock in the morning at LANECO Energy center, Tubod,
Lanao del Norte. The KP is championed by Cabinet Secretary Jun Evasco for the
good governance for transparency and accountability especially against
corruption.
During
the public hearing, Atty. Rodulfo Louie V. Mabalot, Energy Regulatory
Commission (ERC) Heading, presided the public hearing. The SMCPC were
represented by Atty. Abeleno Cedo III, legal officer and Mr. Alberto Reyes,
spokesperson and for LANECO was represented by the Acting General Manager, Mr.
Sherwin Mañada.
Most
of the consumers attended the public hearing were KP members. It was observed
that the ERC did not acknowledge the KP members as interveners. The hearing was
understood to be a compliance to the approval of the joint application of the power
supply contract between the LANECO and SMCPC submitted to the ERC. However,
most of the previous ERC public hearings were presided by the ERC Commissioner
to legally appreciate the proceedings by the person in authority.
Most
of the KP members concerns are the sky rocketed power rate increase in December
2016 as high as PhP15.00 per kWh from PhP9.00 per kWh without prior notice to consumers.
It was allege that the LANECO management decrease power rate to PhP13.00 per
kWh due to flooded complaints. Then currently allegedly the power rate was decrease
to approximately PhP12.00 per kWh. The KP members also complained the
rationality of the contract because LANECO have an existing contract with the
current power suppliers to purchase 12 MW but only 8 MW will be consumed at any
given time in a month. Then here comes the additional 5 MW from SMCPC to have a
total of 17 MW. Therefore, the LANECO member-consumers will pay the excess
power even it was not consumed. All these actions are injustice to the member-consumers that need to be attended.
The LANECO member-consumers are calling the attention of the LANECO officials to refrain the power rate to PhP9.00 per kWh because the power rate increased in December 2016 had no basis and illegal.
The LANECO member-consumers are calling the attention of the LANECO officials to refrain the power rate to PhP9.00 per kWh because the power rate increased in December 2016 had no basis and illegal.
No comments:
Post a Comment